Chemical Manufacturing – Solstice HFO-1234zd Project – Phase 1

Chemical Manufacturing – Solstice HFO-1234zd Project – Phase 1
Chemical Manufacturing – Solstice HFO-1234zd Project – Phase 1

Scope: Early FEL planning for construction of a new process for the manufacture of a Low Global Warming Potential product used in the production of a near “drop-in” replacement of HFC-245fa refrigerant.

Budget:  $110MM

Duration:  24 Months

Highlights:  FEL planning, scheduling, analysis of trending similar projects globally and development of a robust plan of execution for engineering design and construction.

Mitigations/Successes:  Successfully developed analyses to support recommendations for senior stakeholders to place a hold on the project instead of continuing to expend capital resources.  A second analysis was performed on alternatives culminating in a similar recommendation.

Delivered Project Safely, On-time and On-Budget.