Scope: Construct new Benzene Saturation Unit, new Naphtha Fractionation Unit, and enlarge Hydrogen Plant capacity.
Budget: $115MM
Durection: 30 Months
Completed 1 month early
Highlights: Civil, mechanical, electrical, modular construction and setting, heavy haul & lift, tank geodesic dome
Mitigations/Successes: Thorough planning and off-site Modular Construction minimized risks; no project contingency budget used. Rigorous Earned Value methodology was used to measure productivity, predict cost and validate schedule.
Delivered Project Safely, one month ahead of schedule and 12 % under budget.