Scope: Installation of ultra-low sulfur gasoline unit to meet EPA gasoline requirements. Installation of Hydrogen recovery unit to support ULSG unit operation.
Budget: $87MM
Duration: 18 Months
Highlights: Civil, mechanical, structural, electrical, vessel and equipment setting, tie-ins to existing systems.
Mitigations/Successes: Accurately installed complex Hydrogen recovery compressor equipment foundation system. Earned Value methodology was used to measure productivity, predict cost and validate schedule. On track to meet plant turnaround schedule.