A $100M-a-year capital portfolio, turned around

An owner’s annual capital portfolio was spending more than it earned. Executrek put one delivery system across it, and within 9–10 months the portfolio was performing to plan.

Budget
$100M per year
Duration
9–10 months
Status
Completed
Client
Confidential owner
Power plant cooling towers under transmission lines
Cost performance index (CPI)
0.80 → 1.00
Schedule performance index (SPI)
0.84 → 0.98
Productivity factor
0.82 → 0.96

Before and after, 9–10 months apart

The project

The portfolio spent about $100M a year across many projects. A cost performance index of 0.80 meant every dollar was buying 80 cents of progress.

What we did

Executrek put one delivery system across the portfolio: earned value on every project, field-verified progress, weekly forecasts and change control.

How we handled it

Many projects, many contractors and no common measure of progress. Every project was brought onto the same earned-value basis so problems could be compared and fixed project by project.

Results

  • Cost performance index from 0.80 to 1.00
  • Schedule performance index from 0.84 to 0.98
  • Productivity factor from 0.82 to 0.96
  • Measured on actual portfolio data
Need more detail on this kind of project? Many of our engagements are confidential, so we share specifics directly. sales@executrekusa.com · (844) 466-8735

Tell us about your program.

A new capital project, a portfolio that needs a delivery system, or a project that has stalled: call or write, and a senior member of the team will get back to you.

(844) 466-8735sales@executrekusa.com
317 George Street, Suite 320, New Brunswick, NJ 08901More ways to reach us