Diabetes API facility, modular construction
Schedule expedited by 3 months.
- Budget
- $1.83B
- Duration
- 24 months
- Status
- Completed
- Client
- Confidential client

The project
Construction of a new pharmaceutical manufacturing facility designed to produce a next-generation diabetes drug and applicator for a confidential client.
What we provided
- On site: vendor oversight, QA inspection, project controls
- Home office: contracting, procurement support, project controls platform
What we did
The team developed and maintained a Supplier Supervision Program to monitor and enforce schedule, cost, quality and constructability compliance across a large multi-vendor offsite fabrication program.
How we handled it
The schedule was expedited by 3 months by identifying critical activities early enough to mitigate them before they hit the fabrication schedule. The risk of installing engineered equipment was reduced by setting shipping priorities and installation scopes with each vendor.
Results
- Vendor cost performance improved by 8%
- Schedule performance improved by 6%
- Number of changes reduced by 12%
- Schedule expedited by 3 months