Low-GWP chemical manufacturing, phase 2
Cost and schedule baseline managed within 1% accuracy.
- Budget
- $220M
- Duration
- 36 months
- Status
- Completed
- Client
- Confidential client

The project
A new manufacturing process for a low global warming potential product used in a near drop-in replacement for HFC-245fa refrigerant: a new structure, reactor vessel, piping, raw material and product storage, truck loading and unloading, and a thermal oxidizer.
What we did
Built next to another major construction project already underway: civil, mechanical, structural and electrical work, reactor setting, automation, multiple tie-ins and railroad coordination, with an elevated process structure inside the battery limits of a tight operating area.
How we handled it
Executrek developed and maintained cost reporting and engineering progress with earned value by discipline, flagging issues in advance, and set the labor requirements and schedule for construction and commissioning ahead of time.
Results
- Project cost and schedule baseline managed within 1% accuracy