New pharmaceutical manufacturing facility
3-month schedule compression in detailed design.
- Budget
- $1.55B
- Duration
- 30 months
- Status
- Completed
- Client
- Confidential client

The project
A new pharmaceutical manufacturing facility designed to produce drugs for several diseases, including Alzheimer’s disease. Engineering was performed on 3 continents in 5 countries.
What we provided
- On site: EPC contractor oversight, project consulting, project controls, project management, vendor oversight
- Home office: contracting, procurement support, project controls platform
What we did
As the owner’s agents, the Executrek team put an earned-value based project management and controls plan in place, issued weekly analysis that found many time and cost savings, and ran vendor oversight for every specialty equipment manufacturer on a $300M critical-path scope.
How we handled it
Integrating project controls with data analysis gave the owner unique insight through detailed design and construction. Poor SPI, CPI and productivity values were caught early, so the owner and the EPC firm could remove bottlenecks before the following disciplines were hit.
Results
- 3-month schedule compression in detailed design
- 5% reduction in cost growth
- Vendor oversight kept equipment delivery on time