Chemicals · Confidential client
Low-GWP chemical manufacturing, phase 1
Analysis that kept capital from going into the wrong plan.
- Budget
- $110M
- Duration
- 24 months
- Status
- Completed
- Client
- Confidential client

The project
Early front-end planning for a new process to make a low global warming potential product used in a near drop-in replacement for HFC-245fa refrigerant.
What we did
Front-end planning, scheduling, analysis of how similar projects had trended worldwide, and a full execution plan for engineering design and construction.
How we handled it
Executrek’s analyses supported a recommendation to senior stakeholders to put the project on hold instead of continuing to spend capital. A second analysis of the alternatives reached a similar recommendation.
Results
- Two independent analyses for senior stakeholders
- Capital held back instead of spent on a plan that did not hold up